Paper Title Design of Work Breakdown Structure to Interlock Cost Estimation and Process Management in Bridge construction

AUTHORS

Hong-Tae Park,Department of Civil Engineering, Kongju National University, 275 Budae-dong, Seobuk-gu, Cheonan-si, Chungnam 331-717, Republic of Korea
Boo-Hyung Lee,Department of Computer Science & Engineering, Kongju National University, 275 Budae-dong, Seobuk-gu, Cheonan-si, Chungnam 331-717, Republic of Korea

ABSTRACT

In this study, we proposed the efficient DB construction process to interlock cost estimation and process management in bridge construction. In the proposed system, construction process is divided into five hierarchical levels that are milestone network & cost analysis, skeleton network & cost analysis (sub network & cost analysis), frag network & cost analysis and cost estimating. Milestone network & cost analysis level is the highest level and cost estimating level is the lowest level. Each level is designed as DB structure so that cost calculation by level is easy and project management is efficient.

 

KEYWORDS

DB construction process, Five hierarchical level, Cost estimation, Project management

REFERENCES

[1]     Can J., “Principles of classification,” NBS-UK, (1997)
[2]     http://www.buildingsmart.org/standards/standards-library-tools-services/data-dictionary/
[3]     Jorgensen K., “A Classification of building object types-misconceptions, challenges and opportunities,” Proceedings of CIB W78-W102 International,. Conference. Sophia Antipolis, France; 26-28 October, http://2011-cibw078-w102.cstb.fr/papers/Paper-24.pdf, (2011)
[4]     J. H. Park, H. T. Park, and Y. B. Jeon, “The development of factor model based on actual work cost for golf courses,” Journal of The Korea Academia-Industrial Cooperation Society, February, pp.620-627, (2010)
[5]     G. H. Kim, “Research on power plant construction cost forecasting model using the construction model of a similar work,” Chung-Ang University, December, pp.79-99, (1988)
[6]     B. S. Kim, “The basic design Cost Estimation Model for RC rigid frame bridge steps,” Journal of Korea Construction Engineering and Management, March, pp.111-119, (2009)
[7]     B. H. Lee, “Construction cost estimating for project control,” Gumi Publishers, November, pp.325-332, (1992)
[8]     H.T Park and B.H Lee, “WBS-based hierarchical classification and its DB modeling of all construction information for apartment house,” International Journal of Smart Home, vol.9, no.2, pp.133-142, (2015) DOI: 10.14257/ijsh.2015.9.2.12(CrossRef)(Google Scholar)

CITATION

  • APA:
    Park,H.T.& Lee,B.H.(2019). Paper Title Design of Work Breakdown Structure to Interlock Cost Estimation and Process Management in Bridge construction . International Journal of ICT-aided Architecture and Civil Engineering, 6(1), 19-24. 10.21742/IJIACE.2019.6.1.04
  • Harvard:
    Park,H.T., Lee,B.H.(2019). "Paper Title Design of Work Breakdown Structure to Interlock Cost Estimation and Process Management in Bridge construction ". International Journal of ICT-aided Architecture and Civil Engineering, 6(1), pp.19-24. doi:10.21742/IJIACE.2019.6.1.04
  • IEEE:
    [1] H.T.Park, B.H.Lee, "Paper Title Design of Work Breakdown Structure to Interlock Cost Estimation and Process Management in Bridge construction ". International Journal of ICT-aided Architecture and Civil Engineering, vol.6, no.1, pp.19-24, Nov. 2019
  • MLA:
    Park Hong-Tae and Lee Boo-Hyung. "Paper Title Design of Work Breakdown Structure to Interlock Cost Estimation and Process Management in Bridge construction ". International Journal of ICT-aided Architecture and Civil Engineering, vol.6, no.1, Nov. 2019, pp.19-24, doi:10.21742/IJIACE.2019.6.1.04

ISSUE INFO

  • Volume 6, No. 1, 2019
  • ISSN(p):2205-8516
  • ISSN(e):2207-5216
  • Published:Nov. 2019

DOWNLOAD